• Brockman B2-B4 Access Road – Stage 3

Brockman B2-B4 Access Road – Stage 3

Brockman B2-B4 Access Road – Stage 3

Category: Mining / Construction

Principal: Rio Tinto

Client: Brierty Limited

Duration: 2015

Location: Brockman Mine Site - West of Tom Price

Project Description:

The project includes 7.5km of road alignment, comprising 205,000m3 of general fill, 3000m of culverts, and 65 Ha of clearing for the alignment and borrow pits, and 23,000m3 of basecourse…

Survey Scope:

ST Spatial was engaged Brierty to be responsible for the setout and as constructed drawings for the site. This included bulk earthworks, road alignment, culverts as well as volume surveys and infrastructure. ST Spatial was also responsible for the data and the ongoing support for the machine control systems on the various earthmoving plant on site.
Rio Tinto then engaged ST Spatial to complete the ground surveys for the next phase of the project. This data was then used by GHD to design the next section.