Category: Mining / Construction
Principal: Rio Tinto Iron Ore
Client: Brierty
Duration: 2016-2017
Location: Marandoo Mine, Pilbara Region
Project Description:
Survey Scope:
ST Spatial managed bulk volume calculations and design model modifications. ST Spatial played an integral part in managing haul circuits to achieve maximum production rates for bulk earthworks. Surveyors managed a fleet of machine control plant consisting of dozers, graders and excavators Compliance surveys, end of month quantity surveys and reporting. ST Spatial also completed setout for bulk and detailed earthworks and piping instalment.