Category: Government / Infrastructure
Principal: Water Corporation
Client: Cape
Duration: 2016
Location: Narembeen, WA
Project Description:
Supply and Install West Narembeen Tank to Narembeen Town Gravity Supply Main:
– 10.2KM of DN250mm HDPE
– 2.7KM of DN200mm HDPE
– 2.4KM of DN125mm HDPE
Upgrade of pump stations at West Narembeen, Belka, and Wadderin Tank Pump Station
Survey Scope:
ST Spatial was engaged by Cape to complete the survey setout for the pipeline, clearing area extents, pump station civil concrete works and the as-constructed drawing for the pipework installed on site to Water Corporation standards.