• Shenton Park 132/11 kV Zone Substation

Shenton Park 132/11 kV Zone Substation

Shenton Park 132/11 kV Zone Substation

Category: Government / Infrastructure, Power Infrastructure

Principal: Western Power

Client: UGL

Duration: 2014 - 2015

Location: Shenton Park, Perth

Project Description:

A new 132/11 kV substation was constructed on the existing 66/6/6kV substation site as well as an area of crown reserve adjacent to the existing site. The proposed substation development has an estimated cost of $49 million. The target completion date for the Shenton Park substation expansion is late 2015. The existing 66 kV plant will be decommissioned and removed in 2017.

Survey Scope:

ST Spatial was engaged in the initial stages of the project, right through to the as-built sign off.  ST Spatial was responsible for the placement of all concrete footings, pedestals, steelwork and substation components as well as as-constructed surveys of all infrastructure on site.