Category: Mining / Construction, Power Infrastructure
Principal: Talison
Client: Genus
Duration: 2022-2023
Location: Greenbushes
Project Description:
This project involves the construction of a 132 Kilo-Volt electrical supply Power Line to support the mine-site expansion operations, which includes the operation of new production facilities. The proposed Power Line route will extend from the Hester Road Western Power substation, just east of the Bridgetown Golf Course, to the intersection of South-West Highway and Forest Park Avenue, where it will then cross the highway heading directly west where it will join the Mine Power Line infrastructure corridor, within the Mine Development Envelope.
Survey Scope:
ST Spatial was contracted to handle the setout and positioning of bolts for the construction of 22 power poles, as well as conducting the final as-constructed surveys for all infrastructure installed on site.